Last week DoD let contractors hire a CPA firm to review their earned value management system.

For as long as I’ve been doing EVM, DCMA has been the one reviewing EVMS on DoD contracts. That’s no longer the only option.

To be fair to DoD, I understand why they did it. Above a certain threshold, your system still has to be validated. The question is when. That validation can come well into the first few years of a program, and DCMA has only so many people. Still, I don’t think most contractors, or most CPA firms, have read what the new clause actually requires.

What changed

The change is in Class Deviation 2027-O0001, Streamlining Contractor Business Systems. It rewrites the clauses for all six contractor business systems. The new EVMS clause is DFARS 252.234-7999.

Paragraph (d) is the new part. It starts with “If the Contractor has a registered independent public accounting firm,” and that condition matters. You only get the option if your financial statements got a clean audit opinion, with no reported material weaknesses that affect government contracts.

If you qualify, and the contracting officer says a review is needed, you get to choose. The government does it, or you hire an independent public accountant (IPA) to do a third-party review. The clause doesn’t put a dollar limit on that choice.

The dollar tiers are still there, but they now decide how much the government looks at your system after it’s approved. From $100 million up to $275 million, there are no more compliance reviews on that contract unless the contracting officer or the portfolio acquisition executive sees specific risk or suspect reporting quality. At $275 million and up on major development and long-duration production programs, the contracting officer formally verifies the system and keeps doing risk-based compliance reviews after that.

Paragraph (e) sets the rules for the IPA route. The review has to follow government auditing standards (GAGAS) as an attestation engagement. The IPA sends its report straight to the contracting officer. If the report is clean, the government relies on it and won’t re-review your system unless there are signs of fraud, material misstatement or material risk.

That last part is the big one. A clean IPA report carries real weight.

The clause also says the review should happen during the Integrated Baseline Review, “as practical.” Frankly, that’s a bad idea, and it’s the same worry I had when the validation memo came out. An IBR is about the work. The government and the contractor are supposed to come out of it agreeing on scope, budget, schedule and risk. Put a system audit in the same room and the IBR loses that focus. It ends up being all about the system.

That doesn’t mean the system is invisible at an IBR. Sometimes it’s pretty clear a system isn’t working, and an auditor can note that. But the IBR shouldn’t be when the audit takes place. I don’t think that part will last.

What didn’t change

You still need a system that follows the EIA-748 guidelines. The new clause changes who reviews your system, not what it has to do.

The contracting officer still decides whether a review is needed. You don’t get to order one up on your own schedule.

And the IPA route has limits. Paragraph (e) says a third-party review can’t be used to close out corrective actions the government already identified, and it can’t release payments the government is withholding. So if DCMA already has open findings on your system, hiring a CPA firm won’t make them go away. You still have to work those through with the government.

Not everyone qualifies, either. If your last financial audit had problems, this door is closed and you’re back to a government review.

My guess is some contractors will hear “we can use a CPA firm now” and stop there. Read paragraphs (c), (d) and (e) before you plan around it.

Who actually knows EVMS?

CPA firms know how to audit. Plenty of them already review accounting systems, estimating systems and purchasing systems for government contractors, and they’re good at it.

EVMS is a different animal. A real review means sitting in CAM interviews and doing a single point trace through the artifacts, from the work authorization to the schedule to the cost data. It means knowing whether a variance analysis gets to the real root cause, and whether the corrective actions are actually being worked.

That’s not something you pick up from the audit manual. It’s not something you pick up from the guidelines either.

GAGAS does let audit firms bring in specialists for work outside their own expertise. So before you pick an IPA, ask who on their team will do the EVMS part. That person needs to be a practitioner, someone who has actually worked in an EVMS on real programs. Not someone who read the guidelines and came away with the wrong interpretation.

I’ve seen what happens when a reviewer applies their own interpretation of a guideline. It costs the contractor time and money. Sometimes it’s worse than that. When the finding itself is based on a wrong interpretation, there may be no corrective action that can close it.

Changing a few processes after a review is normal. That’s part of having a system. But when you’ve written a system that meets the guidelines and the reviewer misunderstands it, you can end up redesigning your system processes just to satisfy one person’s interpretation.

That was never the reason for the standard.

A clean report from a team that didn’t know what to look for isn’t worth much. Your customer is going to find out how your system really works eventually, and you’d rather it be before the program is in trouble.

What to do now

First, know which tier your contracts fall in. That tells you how much review to expect once your system is approved.

Next, look at your last financial statement audit. Was the opinion clean? Were any material weaknesses reported that touch your government contracts? If the opinion wasn’t clean, or there were material weaknesses, the IPA route isn’t open to you, and your next review will be a government review.

If you do qualify, look at where your EVMS stands with the government today. Open findings or a payment withhold stay with DCMA. Get those closed first.

Then look at your own system. Does your system description still match how your people actually work? Pull a control account and do your own single point trace. It’s a lot cheaper to find the gaps yourself than to have a reviewer find them, no matter who that reviewer works for.

If you decide to go the IPA route, talk to your contracting officer early. Ask the CPA firm who’ll do the EVMS work, and what programs they’ve actually supported.

Who pays for it? When DCMA does the review, it comes out of DCMA’s budget, not your contracts. An IPA review is different. Outside accounting and consulting fees are generally allowable when they’re reasonable, so the cost will land on your contracts, either charged directly to the program that triggered the review or spread through your indirect rates. Plan for it.

That doesn’t make the IPA route a bad choice. It may well be the faster one. DCMA has a big backlog, and a government review can come well into the first few years of a program. With an IPA, you’re not waiting in that line. A clean report early in the program is worth a lot. Just go in knowing what it costs and who’s doing the EVMS work.

And keep an eye on this. It’s a class deviation, so the details could still change before it’s written into the regulations.

If you’re a CPA firm looking at this work

You already know GAGAS and attestation engagements. What you may not have is someone who has worked inside an EVMS on real programs. That’s what we bring. We can join your review team as the EVMS specialists, so the review gets done by people who know what they’re looking at.

Whether you’re a contractor deciding which route makes sense for your system, or a CPA firm that needs practical EVMS experience on your team, get in touch.